Requirement is to run SNP heuristic for a material which has BOM.However, not all components have MRP type as X0.
Ex:
Parent Material P1 has MRP Type X0
P1 has three components C1, C2, & C3 which has MRP Type X0, PD, X0 respectively.
CIF is configured to have materials with MRP Type X0. So only P1, C1, C3 materials will exist in APO product master.
now when SNP heuristic is run, it will generate dependent demand for components C1, C3. As component C2 will not be in APO product master, does dependent demand gets generated for this component C2 when SNP heuristic is run ?
Whatu2019s the standard approach ?
Thanks