Hi,
We are maintaining the capacity for “SNP Bucket Capacity” with number of periods as 7 days for resources in SAP APO.
However when we CIF the PDS the fixed duration for the activity is getting populated as 1 Day instead of 7 Days.
I have attached the document with setting for reference, request you to provide your input to resolve the issue.
Thanks,
Sanjog Mishrikotkar