Hi All,

 

I have the following problem in the CTM application. I have one location with a customer order and a firmed planned order. The firmed planned order has a goods recipe date one month later than the goods issue date of the sales order. When I run the CTM another planned order is created at the goods issue date of the sales order. I expected that the firmed planned order has been taken by CTM to fulfill the demand. 

 

If have therefore allowed the late demand fulfillment for 100 days and set the strategy to the domino strategy.

Has anybody an idea what parameter I have to set.

 

Best Regards